Replacing two 6 kV high-voltage installations
Market: Energy
Tebulo was responsible for replacing two outdated 6kV single-rail installations from 1966 and installing two choke coils.
Technology & Activities
Techniques:
Energy:
- Low Voltage
- Network simulation
- Civil Engineering
Automation:
- IED (Intelligent Electronic Device)
- Control Systems
Activities:
- Advice
- Coordination of electrical work
- Project guidance
- Simulation of the high-voltage network
Project description
A paper mill in North Holland has successfully completed the renovation of part of its medium-voltage network. Tebulo Engineering was involved in the project management. The project was initiated to replace two 6kV high-voltage installations dating from 1966. Following the replacement of the high-voltage installations, two new choke stations were also installed and new high-voltage cables were laid. A 3D model of the new choke station was first created.
The conversion was completed in a period of 1.5 weeks, with 24-hour days. However, the preparation time took several months. Tebulo Engineering, in collaboration with the client, performed the FAT (Full Technical Assessment) for both high-voltage installations beforehand. Tebulo also provided consultancy services for the engineering.